Clearance Sheet C2023-002310

Clearance Sheet is Over 180 Days

Contractor: HOLLETT, BRADLEY ANSON
Unpaid $0.00(); Paid $15,383.95(01564568,1471615,1452618,1458994)
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
22309170 10/16/2023 9:11:06 AMU FPL BRUTON, JASON WILLIAM00[ FEEDER SERVICE PANEL Amps 200 - MAIN SERVICE PANEL Amps 400 - ]
32305645 10/13/2023 2:42:34 PM PARKER, BARRY EUGENE00[ NEW CONSTRUCTION 34 - ]
42403393 3/20/2024 12:47:02 PMA FOURAKER, GERALD A00[ NEW HVAC Valuation 1 - ]
62400159 5/3/2024 8:08:28 AMSPKLSTARLING, DUSTIN00[ SPRINKLER SYSTEM unit 398 - ]
12312550 9/14/2023 9:41:14 AM327HOLLETT, BRADLEY ANSON00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
FIRE MARSHALL REVIEW6/22/2023 dlyons7/13/2023 VVitorivvitoriRejected 18 Plan Review
BLDG PLAN REVIEWER7/14/2023 bmsmith7/24/2023 jedwardsjedwardsRejected 2 Plan Review
FIRE RESUB MARSHAL REVIEW8/23/2023 lnewton8/31/2023 VVitorivvitoriApproved ALL NEW SET OF PLANS 0 Plan Review
BLDG RESUBMIT8/31/2023 bmsmith9/5/2023 jedwardsjedwardsApproved 2 Plan Review
FIRE SPRINKLER SYSTEM2/7/2024 lnewton2/20/2024 VVitorivvitoriRejected 4 Plan Review
FIRE RESUB SPRINKLER SYSTEM2/27/2024 lnewton3/14/2024 VVitorivvitoriRejected 7 Plan Review
 4/11/2024 dlyons4/11/2024 sschnellenbergersschnellenbergerRejected See comments in plan review. 4 Plan Review
FIRE RESUB SPRINKLER SYSTEM4/15/2024 lnewton4/29/2024 VVitorivvitoriApproved 0 Plan Review
FIRE ALARM SYSTEM7/26/2024 dlyons8/9/2024 VVitorivvitoriRejected 5 Plan Review
FIRE MARSHAL REVISION8/1/2024 dlyons8/20/2024 PWebbpwebbRejected Address holds on interior windows, added washer, dryer and janitor sink rm 123, converted rms 121-127 to night security guard quarters 5 Plan Review
 8/14/2024 lnewton8/15/2024 sschnellenbergersschnellenbergerApproved 0 Plan Review
BLDG REVISION8/21/2024 jcrodriguez8/21/2024 jedwardsjedwardsRejected Address holds on interior windows, added washer, dryer and janitor sink rm 123, converted rms 121-127 to night security guard quarters 2 Plan Review
FIRE MARSHALL REVIEW9/4/2024 dlyons9/4/2024 RDowlingrdowlingApproved BDA Test 0 Plan Review
FIRE RESUB ALARM SYSTEM9/9/2024 lnewton    5 Review Pending


Notes

Note DtNote
  Emailed rejected fire comments 7/13/2023 - plans sent to bldg. dept - lln
  EMAILED REJECTION COMMENTS; PLANS SENT BACK TO FIRE 07/24/2023 BMS
  Received plans back from Bldg. Dept. put plans in box# 102 7/25/23 dml
  Emailed approved Fire comments, plans routed to the Bldg. Dept. 8/31/23 dml
  Emailed Rejected Sprinkler Comments 2/22/2024 - Cubby "S" - lln
  Emailed rejected fire sprinkler comments, put plans in cubby "S" 3/14/24 dml
  Emailed Rejected Fire Comments for Underground 4/12/2024 - Cubby "R" - lln
  Updated job valuation to include increase amount for revision- 8/1/24 from 4,997,900 to 5,012,900 dml
  Emailed Rejected Fire Alarm Comments 8/9/2024 - Cubby "W" - lln
  Emailed Rejected fire Comments for Revision 8/20/2024 - Plans sent to bldg. dept - lln
  E-MAILED COMMENTS- REJECTED REVISION ROUTED BACK TO FIRE
  Received plans back from bldg. dept. put in box# 99 8/21/24 dml