Preliminary reviews are one time reviews submitted prior to approval of a clearance sheet and site plan. Because of this, and the documentation and plans are usually insufficient and incomplete, a full review cannot be accomplished without the possibility of adding additional comments at time of future submittals.

7/10/2024 shillyard

 One (1) set of plans for 20 Clearance Sheets (??? ~ ???). This comment will not be signed off until all Clearance Sheets have all of their comments addressed

7/10/2024 shillyard

On sheet P004, the code cycle stated is 2020 FBC-Fuel Gas. Please correct to reflect 2023 FBC-Fuel Gas

7/10/2024 shillyard

The NEC code cycle on sheet G000 is incorrect. It is referenced as 2017, the code cycle currently being used by St. Johns County is the NEC 2020

7/10/2024 shillyard

The building numbers on sheet G002 doesn't match the building numbers on sheets E004 and P004. Please correct to reflect the correct building numbers

7/10/2024 shillyard
The truss drawings shall be signed and sealed. Provide two sets of signed and sealed truss drawings and truss layout approved by the designer of record as per TPI. 7/10/2024 shillyard

Please update drawings to show the building code review for Garage 5/Property Management Facility.

7/10/2024 shillyard
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal.
If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again.
ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
7/10/2024 shillyard