SJC Home
Clearance Sheet C2024-003701

 Department IssuesSigned OffIntl

1. The Architectural plans must be sealed, signed and dated by an Architect registered in the state of Florida.

11/26/2024 jedwards

2. The Structural plans, Mechanical plans, Electrical plans and Plumbing plans must be sealed, signed and dated by Engineers registered in the state of Florida.

11/26/2024 jedwards

3. The Energy Code that was provided within the set of plans is not complete. The Envelope Compliance Certificate was the only item that was provided and it was not signed and dated. Please provide 2 copies of the following additional items: Mechanical Compliance Certificate, Exterior Lighting Compliance Certificate and Interior Lighting Compliance Certificate.  Please have a registered design professional with a Florida registration number sign and date all of the documents

11/26/2024 jedwards

4. The plans do not show stair elevations. Please submit code compliant dimensions of all stair elements to include riser height, tread depth, handrail height, handrail extension measurements, guard height and width of the stairways.

11/26/2024 jedwards

5. The Electric Room 135 contains electrical equipment that is rated at 1,600 Amperes. 2020 NEC 110.26(C)(3) states that where equipment rated 800 amperes or more...is installed and there is a personnel door(s) intended for entrance to and egress from the working space...,the door(s) shall open in the direction of egress and be equipped with listed panic hardware or listed fire exit hardware. Please provide the missing panic hardware for this door(s).

11/26/2024 jedwards

6. Please address Fire Services comment #5 regarding the discrepancy between the square footages shown on Sheet G003.

11/26/2024 jedwards

7. The Electrical lighting plan on Sheet E301 is missing exit signs for Doors 132b and 132e.  Please demonstrate compliance with 2023 FBC-Building 1013.1.

11/26/2024 jedwards
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal.
If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again.
ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
11/26/2024 jedwards