SJC Home
Clearance Sheet R1999-004244

Clearance Sheet is Over 180 Days

Contractor: CUNY, PAUL L.
Unpaid $0.00(); Paid $478.30(0207055)
Cert Occ
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
29904080 12/16/1999 12:00:00 AMU JAX4.03 KNUTH, MICHAEL L.00[ MAIN SERVICE PANEL Amps 200 - TEMPORARY POLE 3000 - ]
39902420 12/20/1999 12:00:00 AM NELSON, SCOTT GARY00[ Fixtures Cnt Unit 12 - RETIRED ADM FEE 1 - Sewer 0 - Vacume Breaker Unit 3 - WATER HEATER Unit 1 - ]
40001099 4/19/2000 12:00:00 AM JONES, JAMES GLENN00[ HVAC ChgOut / Repair Valuation 10650 - ]
40001334 5/11/2000 12:00:00 AM WRIGHT, MICHAEL D. 00[ Gas Piping Outlet 2 - Other ME Chrg Amount 1 - ]
19905091 12/15/1999 12:00:00 AM101CUNY, PAUL L. 00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
BLDG PLAN REVIEWER11/19/1999 MH11/19/1999PVRejected JACK POPE REJECTED 0 Plan Review
BLDG RESUBMIT11/23/1999 TM11/29/1999TLOApproved RESUBMIT JACK POPE 0 Plan Review
BLDG PLAN REVIEWER12/23/1999 MH12/2/1999TLOApproved PLAN REVIEWER 0 Plan Review


Notes