8TH EDITION FBC (2023)
| |
| |
|
EARLY POWER LETTER REC'D
| |
2/6/2026 7:32:39 AM
| clschmermund |
|
ENERGIZE BLDG INSPECTION
| |
1/23/2026 12:56:17 PM
| |
|
FEMA FORM REQUIRED
| N/A - PROJECT IN X ZONE |
1/26/2026 11:13:27 AM
| jbrown |
|
HOLD 109 INSP FOR FIRE ALRM PRMT
| |
7/28/2025 8:01:06 AM
| lnewton |
|
HOLD 109 INSP FOR FIRE ALRM PRMT
| FIRE ALARM REVISION TO ADDRESS COMMENT 5 FROM 1/22/26 REVIEW |
| |
|
HOLD 109 INSP FOR FIRE ALRM PRMT
| HOLD FOR FA REVISION DUE TO SHELL BUILDOUT AND REVISION |
| |
|
HOLD 109 INSP FOR FIRE SPRNKLR PRMT
| HOLD FOR SPRINKLER DUE TO SHELL BUILDOUT AND REVISION. |
| |
|
HOLD 109 INSP FOR FIRE SPRNKLR PRMT
| |
8/14/2025 7:21:15 AM
| lnewton |
|
HOLD 109 INSP FOR UNDERGROUND PERMIT
| SIGNED OFF UNDER 12500451 |
10/6/2025 3:59:26 PM
| PWebb |
|
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.
| |
| |
|
HOLD C/O FOR SITE ASBUILT APPROV
| |
| |
|
HOLD C/O: ORIGINAL FINISHED CONST FEMA
| N/A - PROJECT IN X ZONE |
1/26/2026 11:13:33 AM
| jbrown |
|
IMPACT FEE DUE
| |
12/12/2024 9:22:08 AM
| lbrown |
|
INFO NOC-
| 6091//1979 |
2/3/2025 10:19:40 AM
| nmcdowell |
|
LANDSCAPE INSPECTION REQ
| |
| |
|
TERMITE BOND CO
| TURNER PEST/ SOIL |
1/22/2025 3:09:13 PM
| krobshaw |
|
TERMITE PROTECTION CERT OF COMPL
| |
| |
|
CK FOR OUTSTANDING FEES (IMPACT FEES) ON SHELL #12500451
| **BEFORE RELEASING POWER** |
| |
|
HOLD 109 FOR BDA REVISION
| |
| |
|
HOLD 109 FOR HELIPAD
| |
| |
|
HOLD 109 FOR ABOVEGROUND TANK PERMIT
| ADDRESSED UNDER CEP |
10/6/2025 4:00:16 PM
| PWebb |
|
HOLD 105 FOR BDA SYSTEM TEST
| BDA SUBMITTED. |
4/1/2025 4:11:53 PM
| PWebb |
|
HOLD 109 FOR DOOR HARDWARE REVISION.
| ADDRESSED BY PREVIOUS REVISION |
8/26/2025 7:23:36 AM
| PWebb |
|
HOLD 109 FOR REVISION FOR COMMENTS 15, 17, 21 AND 22.
| ADDRESSED BY REVISION DATED 4/1/25 |
4/1/2025 12:33:31 PM
| PWebb |