SJC Home
DescriptionInputDateWho
7th Edition FBC (2020)    
EARLY POWER LETTER REC'D 22310011 11/28/2023 7:34:59 AM kcooper
EARLY POWER LETTER REC'D 22303025 11/28/2023 7:35:22 AM kcooper
ENERGIZE BLDG INSPECTION   11/28/2023 8:19:09 AM air
FEMA FORM REQUIRED PARCEL IN X ZONE, NOT IN AUDIT. 8/22/2023 3:46:33 PM ajordan
HOLD 109 INSP FOR FIRE ALRM PRMT   4/25/2023 1:57:40 PM dlyons
HOLD 109 INSP FOR FIRE SPRNKLR PRMT SEE 3 6 23 APPROVED REVISED LAYOUT 4/26/2023 9:45:16 AM lnewton
HOLD 109 INSP FOR UNDERGROUND PERMIT   2/14/2023 7:58:09 AM dlyons
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.   7/12/2024 9:42:18 AM  
HOLD C/O FOR SITE ASBUILT APPROV   7/23/2024 8:06:34 AM nbradley
HOLD C/O: ORIGINAL FINISHED CONST FEMA PARCEL IN X ZONE, NOT IN AUDIT. 8/22/2023 3:46:43 PM ajordan
IMPACT FEE DUE 23-057873 9/26/2023 1:50:49 PM tclif
INFO NOC- 5705 / 107 3/6/2023 12:50:54 PM clschmermund
LANDSCAPE INSPECTION REQ LANDSCAPE WILL BE CAPTURED AT TIME OF ASBULT 5/8/2024 2:57:07 PM jdegennaro
PAID UTILITY RECEIPT REQUIRED JEA 5/17/2024 2:46:33 PM khart
REINSPECTION FEE 24-032835 5/28/2024 9:17:14 AM tclif
REINSPECTION FEE 24-043093 7/11/2024 5:01:33 PM Lexis
TERMITE BOND CO FLORIDA PEST / SOIL 1/12/2023 11:55:39 AM krobshaw
TERMITE PROTECTION CERT OF COMPL   5/7/2024 1:30:02 PM kcooper
HOD FIRE ALAM FINAL FOR REVISION TO FA FOR BFP SUPERVISION   4/5/2024 6:03:36 AM dfeagle