2007-FL BLDG CODE    
EARLY POWER LETTER REC'D   2/19/2010 8:43:03 AM KHART
ENERGIZE BLDG INSPECTION   2/25/2010 8:37:39 AM KHART
HOLD BLDG FINAL INSP FOR FIRE MARSHAL FINAL.   7/16/2010 4:00:41 PM  
HOLD C/O FOR SITE ASBUILT APPROV OK FOR FINAL BUILDING INSPECTION 11/10/2010 2:49:35 PM vpacetti
IMPACT FEE DUE 10-003793 2/25/2010 1:51:15 PM DKG
INFO NOC- O.R. 3220 PG 651-651 7/21/2009 3:33:25 PM ecannon
LANDSCAPE INSPECTION REQ   7/14/2010 2:20:24 PM  
SEPTIC TANK FINAL REQ release 7/16/2010 12:00:00 AM LAC
TERMITE BOND CO BAKER 8/12/2009 2:44:31 PM KHART
TERMITE PROTECTION CERT OF COMPL   9/23/2010 12:10:39 PM ymontgomery
NEED PLUMBING RISER DIAGRAM PER RFD   12/2/2009 8:57:38 AM khart