Clearance Sheet C2026-001673 |
|
|
|
Contractor:
TASKAN, MEHMET FAHRETTIN |
|
|
Unpaid $0.00(); Paid $32,756.75(01712338,1716019)
|
|
|
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
22604758
| 7/22/2026 1:47:11 PM | U FPL | FIELDS, ALEXANDER KANE | 0 | 0 | [ (11) FEEDER SERVICE PANEL Amps 400 - MAIN SERVICE PANEL Amps 2500 - ] |
|
32603245
| 8/3/2026 11:51:01 AM | | BETROS, STEPHEN MICHAEL JR | 0 | 0 | [ NEW CONSTRUCTION 125 - ] |
|
12608043
| 7/14/2026 5:02:57 PM | 326 | TASKAN, MEHMET FAHRETTIN | 0 | 0 | |
Log
| FIRE MARSHALL REVIEW | 5/5/2026 hsapp | 5/14/2026 PWebb | pwebb | Rejected |
| 65 |
Plan Review
|
| BLDG PLAN REVIEWER | 5/19/2026 krobshaw | 5/22/2026 shillyard | shillyard | Approved |
| 0 |
Plan Review
|
| FIRE RESUB MARSHAL REVIEW | 6/30/2026 hsapp | 7/10/2026 PWebb | pwebb | Approved |
| 0 |
Plan Review
|
| BLDG RESUBMIT | 7/13/2026 kcooper | 7/14/2026 shillyard | shillyard | Approved |
| 0 |
Plan Review
|
| | 8/3/2026 lnewton | 8/5/2026 jlhatcher | jlhatcher | Rejected |
| 10 |
Plan Review
|
| | 8/10/2026 lnewton | 8/11/2026 jlhatcher | jlhatcher | Rejected |
| 3 |
Plan Review
|
| | 8/19/2026 jlhatcher | 8/25/2026 jlhatcher | jlhatcher | Approved |
| 0 |
Plan Review
|
| FIRE MARSHAL REVISION | 8/19/2026 hsapp | 8/31/2026 PWebb | pwebb | Rejected |
REVISION: Structural, Mechanical, Electrical, Misc.
| 2 |
Plan Review
|
| FIRE MARSHAL REVISION | 8/25/2026 lnewton | 8/25/2026 jlhatcher | jlhatcher | Approved |
Revision to address the FP-1 page to match the underground and civil to include 2 FDC's and 12" pipe.
| 0 |
Plan Review
|
| BLDG REVISION | 8/28/2026 bmsmith | 8/31/2026 shillyard | shillyard | Approved |
Revision to address the FP-1 page to match the underground and civil to include 2 FDC's and 12" pipe.
| 0 |
Plan Review
|
| BLDG REVISION | 9/1/2026 bmsmith | 9/2/2026 shillyard | shillyard | Rejected |
REVISION: Structural, Mechanical, Electrical, Misc.
| 2 |
Plan Review
|
Notes
| |
Received Plans Conditionally/Awaiting Pymnt for FPR 5/1/2026 - Under Plan Room Shelf - lln
|
| |
Emailed Rejected Fire Comments 5/15/2026 - Plans routed to Bldg Dept - lln
|
| |
BLDG APPROVED- ROUTED REJECTED PLANS BACK TO FIRE 5/22/26 AH
|
| |
Received plans back from bldg. dept 5/28/2025 - Back Hallway -hs
|
| |
Emailed Approved Fire Comments 7/10/2026 - Plans routed to Bldg Dept - hs
|
| |
Emailed Rejected Underground Comments 8/7/2026 - Cubby "6" - hs
|
| |
Emailed Rejected Underground Comments 8/12/2026 - Cubby "1" - lln
|
| |
Emailed Approved Fire Comments for Revision 8/26/2026 - Plans routed to Bldg Dept - hs
|
| |
Emailed Rejected Fire Revision Comments 8/31/26 - Plans routed to Bldg Dept - hs
|
| |
emailed revision ready in cabinet under TASKAN
|
| |
E-MAILED REJECTION COMMENTS- REJECTED REVISION ROUTED BACK TO FIRE 9/2/26 AH
|
|
|