SJC Home
Clearance Sheet C2026-001673

Contractor: TASKAN, MEHMET FAHRETTIN
Unpaid $0.00(); Paid $32,756.75(01712338,1716019)
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
22604758 7/22/2026 1:47:11 PMU FPL FIELDS, ALEXANDER KANE00[ (11) FEEDER SERVICE PANEL Amps 400 - MAIN SERVICE PANEL Amps 2500 - ]
32603245 8/3/2026 11:51:01 AM BETROS, STEPHEN MICHAEL JR00[ NEW CONSTRUCTION 125 - ]
12608043 7/14/2026 5:02:57 PM326TASKAN, MEHMET FAHRETTIN00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
FIRE MARSHALL REVIEW5/5/2026 hsapp5/14/2026 PWebbpwebbRejected 65 Plan Review
BLDG PLAN REVIEWER5/19/2026 krobshaw5/22/2026 shillyardshillyardApproved 0 Plan Review
FIRE RESUB MARSHAL REVIEW6/30/2026 hsapp7/10/2026 PWebbpwebbApproved 0 Plan Review
BLDG RESUBMIT7/13/2026 kcooper7/14/2026 shillyardshillyardApproved 0 Plan Review
 8/3/2026 lnewton8/5/2026 jlhatcherjlhatcherRejected 10 Plan Review
 8/10/2026 lnewton8/11/2026 jlhatcherjlhatcherRejected 3 Plan Review
 8/19/2026 jlhatcher8/25/2026 jlhatcherjlhatcherApproved 0 Plan Review
FIRE MARSHAL REVISION8/19/2026 hsapp8/31/2026 PWebbpwebbRejected REVISION: Structural, Mechanical, Electrical, Misc. 2 Plan Review
FIRE MARSHAL REVISION8/25/2026 lnewton8/25/2026 jlhatcherjlhatcherApproved Revision to address the FP-1 page to match the underground and civil to include 2 FDC's and 12" pipe. 0 Plan Review
BLDG REVISION8/28/2026 bmsmith8/31/2026 shillyardshillyardApproved Revision to address the FP-1 page to match the underground and civil to include 2 FDC's and 12" pipe. 0 Plan Review
BLDG REVISION9/1/2026 bmsmith9/2/2026 shillyardshillyardRejected REVISION: Structural, Mechanical, Electrical, Misc. 2 Plan Review


Notes

Note DtNote
  Received Plans Conditionally/Awaiting Pymnt for FPR 5/1/2026 - Under Plan Room Shelf - lln
  Emailed Rejected Fire Comments 5/15/2026 - Plans routed to Bldg Dept - lln
  BLDG APPROVED- ROUTED REJECTED PLANS BACK TO FIRE 5/22/26 AH
  Received plans back from bldg. dept 5/28/2025 - Back Hallway -hs
  Emailed Approved Fire Comments 7/10/2026 - Plans routed to Bldg Dept - hs
  Emailed Rejected Underground Comments 8/7/2026 - Cubby "6" - hs
  Emailed Rejected Underground Comments 8/12/2026 - Cubby "1" - lln
  Emailed Approved Fire Comments for Revision 8/26/2026 - Plans routed to Bldg Dept - hs
  Emailed Rejected Fire Revision Comments 8/31/26 - Plans routed to Bldg Dept - hs
  emailed revision ready in cabinet under TASKAN
  E-MAILED REJECTION COMMENTS- REJECTED REVISION ROUTED BACK TO FIRE 9/2/26 AH