Permit #Issue DateInfoContractorPaidDueAssocInfo
22403847 1/1/0001 12:00:00 AMU FPL CRIST, WILLIAM B JR.00 
22403886 5/2/2024 11:54:39 AMU JAX CRIST, WILLIAM B JR.00[ MAIN SERVICE PANEL Amps 300 - ]
22403887 5/2/2024 11:54:40 AMJAX4.03 CRIST, WILLIAM B JR.00[ TEMPORARY POLE 1 - ]
22409198 10/17/2024 2:43:51 PMU JAX MOORE, JASON SCOTT00[ (2) MAIN SERVICE PANEL Amps 150 - ]
22409779 11/1/2024 7:01:10 AMJAX4.03 MOORE, JASON SCOTT00[ TEMPORARY POLE 1 - ]
32403096 5/28/2024 6:50:21 PM HILL, HARRY H00[ NEW CONSTRUCTION 34 - ]
42414246 11/18/2024 12:35:47 PMA DONOVAN II, WILLIAM JOEL00[ NEW HVAC Valuation 0 - ]
42414817 12/3/2024 11:26:52 AMG GRIFFIS, BLAKE00[ GAS PIPING Outlets 9 - ]
82502911 11/6/2025 8:37:58 AM HULIHAN, SCOTT SHANNON00[ SPRINKLER HEADS Units 25 - ]
12400572 1/12/2024 11:18:01 AM101GULLION, DONALD ANTHONY00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
BLDG PLAN REVIEWER1/3/2024 gallen1/3/2024 gallengallenRejected 2 Plan Review
BLDG RESUBMIT1/5/2024 ethurston1/5/2024 gallengallenApproved 0 Plan Review
BLDG REVISION1/23/2025 ahart1/23/2025 gallengallenApproved ADDED HVAC UNIT 0 Plan Review


Notes

Note DtNote
  EMAILED REJECTION COMMENTS; PLANS ON BACK SHELF FOR GULLION(MAX)
  PLACED APPROVED REVISION ON BACK COUNTER FOR MAX