3/16/2023 dlyo |
This Clearance Sheet Has Been Converted From Non Clearance Sheet Number N2022-009221
|
|
Emailed Rejected fire comments 4/14/2023 - plans sent to bldg. dept - lln
|
|
PACKAGE CHECKED OUT
|
|
Emailed approved fire comments, routed plans to Bldg. Dept. 5/25/23 dml
|
|
Emailed rejected fire sprinkler comments, put plans in cubby "B" 6/16/23 dml
|
|
OT# 1452603 $54.00 created for underground review- 6/22/23 dml
|
|
Emailed rejected underground fire comments, plans put in cubby "V" 7/7/23 dml
|
|
Emailed Rejected Fire Alarm Comments 11/7/2023 - Cubby "H" - lln
|
|
Emailed rejected fire comments for Revision addressing generator 12/8/2023 - Revision sent to bldg. dept - lln
|
|
Emailed rejected bldg. comments for revision - Revision sent back to fire 12/8/23 jr
|
|
Received rejected revision "Generator Worksheet & Specs" back from bldg. dept 12/8/2023 - Cubby "M" - lln
|
|
Emailed Rejected Fire Alarm Comments 12/13/2023 - Cubby "H" - lln
|
|
Emailed rejected fire revision comments, routed plans to bldg. dept. 1/18/24 dml
|
|
emailed rejected bldg. comments.// routed plans back to fire. 1/23/24 MRW
|
|
Received revision back from bldg. dept. put plans in box # 83 1/23/24 dml
|
|
Emailed Rejected Fire Comments for BDA 1/26/2024 - Cubby "B" - lln
|
|
Tiffany Lambdin checked out plans for Revision "See Narrative/Structural, Architectural, Plumbing & Electrical Revisions" 2/9/2024 - Paper work in Cubby "M" - lln
|
|
Emailed approved Fire comments, routed plans to bldg. dept. 2/15/24 dml
|
|
emailed approved revision BLDG DEPT comments.// Revision in Large Folded Revision Drawer under Marty.// MRW 2/15/24
|
|
Emailed approved Fire Revision comments, routed plans to bldg. dept. 3/18/24 dml
|
|
EMAILED REJECTION COMMENTS; PLANS SENT BACK TO FIRE-BMS 03/22/24
|
|
Emailed approved Fire Revision comments, routed plans to bldg. dept. 4/23/24 dml
|
|
EMAILED APPROVED REVISION READY FOR PICKUP - REVISION ON TOP OF APPROVED REVISION FILING CABINET UNDER MARTY
|
|
Emailed approved fire revision comments, routed plans to bldg. dept. 5/15/24 dml
|
|
EMAILED REVISION PAYMENT LINK/READY FOR PICKUP. LEFT IN APPROVED REVISIONS UNDER MARTY.
|
|
Emailed Rejected Fire Comments for Revision addressing special locking arrangement 5/22/2024 - plans sent to bldg. dept - lln
|
|
CHECKED PACKAGE OUT TO TIFFANY
|
|
Emailed rejected Fire comments. routed over to Bldg. Dept. 1/3/23 dml
|
|
emailed rejected bldg. comments / routed plans back to fire
|
|
Received plans back from Bldg. Dept. put in box #108 1/6/23 dml
|
|
Melanie Hill checked out Rejected Plans 1/13/2023 - lln
|