Clearance Sheet R2022-000051 |
|
|
Clearance Sheet is Over 180 Days
|
Contractor:
FAVER, WILLIAM KEITH |
|
|
Unpaid $0.00(); Paid $1,332.00(01309929)
|
|
Cert Occ |
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
22206270
| 5/23/2022 2:04:29 PM | U JAX | BREEDEN, SHAWN | 0 | 0 | [ MAIN SERVICE PANEL Amps 200 - ] |
|
22206271
| 5/23/2022 2:02:23 PM | JAX4.03 | BREEDEN, SHAWN | 0 | 0 | [ TEMPORARY POLE 1 - ] |
|
32203799
| 6/10/2022 11:07:41 AM | | NELSON, SCOTT GARY | 0 | 0 | [ NEW CONSTRUCTION 38 - ] |
|
42213460
| 9/15/2022 3:37:13 PM | A | SASSER, JOHN HAWKINS | 0 | 0 | [ NEW HVAC Valuation 7400 - ] |
|
42215814
| 11/7/2022 1:43:18 PM | G | SANTANA, ROBERTO | 0 | 0 | [ GAS PIPING Outlets 13 - ] |
|
12202066
| 2/9/2022 4:21:17 PM | 101 | FAVER, WILLIAM KEITH | 0 | 0 | |
|
12308278
| 6/21/2023 2:28:23 PM | 435 | VICK, BRIAN HARDING | 0 | 0 | |
Log
| BLDG PLAN REVIEWER | 2/3/2022 bbonfanti | 2/4/2022 jdacosta | jdacosta | Approved |
| 0 |
Plan Review
|
| BLDG REVISION | 4/11/2023 ehumphreys | 4/11/2023 bLester | tgoodson | Rejected |
MULTIPLE REVISIONS // SEE REVISION SHEET
| 4 |
Plan Review
|
| BLDG RESUBMIT | 4/13/2023 kturner | 4/14/2023 tgoodson | tgoodson | Approved |
| 0 |
Plan Review
|
| PENDING PERMIT ISSUES | 11/20/2023 bmsmith | 11/27/2023 tgoodson | tgoodson | Approved |
Spray foam affidavit report
| 0 |
Plan Review
|
| PENDING PERMIT ISSUES | 5/2/2024 jcrodriguez | 5/2/2024 jbrown | jbrown | Approved |
F/C FEMA
| 0 |
Plan Review
|
Notes
| |
Plans on shelf under favor: resubmitted 4/13/23
|
| |
APPROVED REVISION IN DRAWER UNDER FAVER
|
| |
approved revision in drawer under Faver.// email sent.
|
|
|