SJC Home
Clearance Sheet C2008-001618

Clearance Sheet is Over 180 Days

Contractor: YOUNG, TIMOTHY WAYNE
Unpaid $0.00(); Paid $4,753.72(0510506)
Cert Occ
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
20900127 1/20/2009 11:50:29 AMO JAX 3.05 PATRICK, JOSEPH C.00[ FEEDER SERVICE PANEL Amps 400 - FEEDER SERVICE PANEL Amps 300 - FEEDER SERVICE PANEL Amps 200 - (2) FEEDER SERVICE PANEL Amps 150 - FEEDER SERVICE PANEL Amps 100 - MAIN SERVICE PANEL Amps 800 - TEMPORARY POLE 1 - ]
30900226 2/25/2009 2:31:15 PM JOHNSTON, ISAAC WALTER00[ BACKFLOW PROTECTIVE DEVICE Unit 4 - FIXTURES COUNT 45 - SEWER Count 1 - WATER HEATER Unit 2 - ]
30900550 4/15/2009 12:29:53 PM BILLINGS, BRADFORD LEE00[ SEWER Count 1 - ]
40902165 7/6/2009 10:59:53 AMA OKEEFE, MICHAEL GREGORY00[ NEW HVAC Valuation 203810 - ]
60900097 6/9/2009 10:53:07 AMALRMGREIS, ROBERT C00[ FIRE ALARM Devices 90 - ]
60900122 6/12/2009 9:38:09 AMSPKLBENDER, CHARLES A00[ SPRINKLER SYSTEM unit 277 - ]
10805811 10/16/2008 9:35:29 AM319YOUNG, TIMOTHY WAYNE00 
10901497 4/17/2009 9:49:54 AM500HERNANDEZ, SANTOS L00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
FIRE MARSHALL REVIEW8/12/2008 tbrunson8/19/2008 smurraysmurrayRejected 10 Plan Review
BLDG PLAN REVIEWER8/25/2008 dstratton8/25/2008 dstrattondstrattonRejected 1 Plan Review
FIRE RESUB MARSHAL REVIEW9/11/2008 ktaing9/12/2008 smurraysmurrayApproved sent to SLM 0 Plan Review
BLDG RESUBMIT9/16/2008 tbrunson9/16/2008 dstrattondstrattonRejected 1 Plan Review
BLDG RESUBMIT10/15/2008 dstratton10/15/2008 dstrattondstrattonApproved 0 Plan Review
BLDG REVISION2/19/2009 tbrunson2/19/2009 dstrattondstrattonApproved TRUSS/ELEC/MECH 0 Plan Review
FIRE MARSHALL REVIEW2/19/2009 dstratton2/20/2009 smurraysmurrayApproved Revision mechanical and electrical 0 Plan Review
FIRE ALARM SYSTEM4/21/2009 crecla4/22/2009 jruleyjruleyApproved fire alarm 0 Plan Review
FIRE SPRINKLER SYSTEM6/4/2009 cgalloway6/5/2009 smurraysmurrayPending need fire pump info 1 Plan Review
BLDG REVISION6/8/2009 cmanucy6/8/2009 dstrattonDRSApproved CURTAIN WALL CALCULATIONS 0 Plan Review
FIRE MARSHAL REVISION6/8/2009 smurray6/8/2009 smurraysmurrayApproved Curtain wall 0 Plan Review
FIRE RESUB SPRINKLER SYSTEM6/10/2009 cmanucy6/11/2009 smurraysmurrayApproved Sprinkler & Fire Pump 0 Plan Review
BLDG REVISION7/24/2009 smurray7/27/2009 jpaulajpaulaApproved Truss revision, changed valted ceiling pitch 0 Plan Review
FIRE MARSHAL REVISION7/24/2009 ktaing7/24/2009 smurraysmurrayPending Truss revision 1 Plan Review
FIRE MARSHAL REVISION7/27/2009 smurray7/27/2009 smurraysmurrayApproved truss 0 Plan Review
FIRE MARSHAL REVISION8/4/2009 abutler8/5/2009 smurraysmurrayApproved TRUSS ENGIN #2 0 Plan Review
BLDG REVISION8/5/2009 smurray8/6/2009 darlingtondarlingtonRejected Truss revision #2 1 Plan Review
BLDG RESUBMIT8/24/2009 cgalloway8/26/2009 darlingtondarlingtonApproved RESUBMIT OF REJECTED REVISION, SENT TO DJA 0 Plan Review
FIRE MARSHAL REVISION8/27/2009 ktaing8/28/2009 pwebbpwebbApproved revision to fire sprinkler;add sprinklers in attic-sent to FM 0 Plan Review


Notes

Note DtNote
8/31/2009 ecannon

APPROVED REVISED PLAN PUT IN DRAWER

8/18/2009 cgalloway

BRIAN CHECKED OUT REJECTED REVISION

8/7/2009 ecannon

DISAPPROVED REVISED PLAN PUT IN DRAWER

8/5/2009 smurray

Sent to Bldg Dept

7/27/2009 ecannon

APPROVED REVISED PLAN PUT IN DRAWER

7/24/2009 smurray

Plan placed on Jim's desk.

6/8/2009 ecannon

APPROVED REVISED PLAN PUT IN DRAWER

6/5/2009 ecannon

REC'D FIRE SPRINKLER PLANS FROM STEPHANIE, PUT ON REJECTED SHELF UNDER BENDER

2/23/2009 EEC APPROVED REVISED PLAN PUT IN DRAWER
2/19/2009 DRS sent to f/m
11/20/2008 JDC PLANS LOCATED ON 3RD FLOOR.
9/17/2008 TGM REJECTED PLANS AT THELMA'S DESK/REJECTED FOR HEIGHT & NEED SEPTIC TANK PERMIT NOTIFIED DOUG
9/16/2008 TEB This Clearance Sheet Has Been Converted From Non Clearance Sheet Number N2008-000357
9/16/2008 TEB SENT CLEARANCE SHEET/SITEPLANS/NOC TO STEPHANIE TO PUT WITH PACKAGE. THEN TO DRS.
9/16/2008 SLM Sent to Dallas
9/12/2008 SLM Although plans approved, plans in Steph's office awaiting clearance sheet.
8/25/2008 EEC REC'D PLANS FROM DALLAS &STEPHANIE,FM, PUT ON REJECTED SHELF
8/19/2008 SLM Plan placed on BD shelf.