SJC Home
Clearance Sheet C2007-001845*001

Clearance Sheet is Over 180 Days

Contractor: WEHBY CHIRUMBOLO, DANA D
Unpaid $0.00(); Paid $617.84(0468836)
Cert Occ
Proj Name: Parcel:
Prop Use Desc: Prop Use:
Contractor ID: Valuation:

Pre:      Street Num:      Street:      Class:      Post:      Zip  Supplemental:   


Expedited Review Required:   

Permit #Issue DateInfoContractorPaidDueAssocInfo
20703805 8/9/2007 1:45:53 PMU JEA SCIOLINO, JOHN MICHAEL00[ MAIN SERVICE PANEL Amps 200 - ]
20704706 8/9/2007 1:45:53 PMU JEA SCIOLINO, JOHN MICHAEL00[ MAIN SERVICE PANEL Amps 200 - ]
30702245 8/8/2007 3:35:42 PM KING, PAUL THOMAS00[ Fixtures Cnt Unit 28 - WATER HEATER Unit 2 - ]
40703904 8/22/2007 1:44:11 PMA CHADDOCK, THOMAS P.00[ New HVAC Valuation 125000 - ]
40704077 9/4/2007 2:08:36 PMH CHADDOCK, THOMAS P.00[ Fire Hood Cnt 1 - Fire Marshal ME Amt 150 - Hood Valuation 6000 - ]
40704513 10/1/2007 2:42:01 PMG SPRADLIN, BELINDA A00[ GAS PIPING Outlets 8 - ]
60700269 9/11/2007 1:59:16 PMSUP KING, KENNETH G00[ Fire Suppression System 1 - ]
60700271 8/9/2007 9:13:56 AMSPKLSWANSON, JOHN P00[ Sprinkler System Heads 38 - ]
10705353 8/7/2007 3:34:09 PM437 WEHBY CHIRUMBOLO, DANA D00 


Log

TypeRcv DtPln Rvwd DtRvwdByStatusCommentOutstanding CommentsPlan Review
BLDG PLAN REVIEWER6/29/2007 crecla7/2/2007 dstrattondstrattonRejected 2 Plan Review
FIRE MARSHALL REVIEW7/2/2007 dstratton7/5/2007 jruleyjruleyRejected Interior Build0ut 1 Plan Review
BLDG RESUBMIT7/6/2007 cmanucy7/6/2007 dstrattondstrattonRejected sent to dallas 1 Plan Review
FIRE RESUB MARSHAL REVIEW7/12/2007 dstratton7/16/2007 jruleyjruleyRejected Resubmitted Plans 1 Plan Review
BLDG RESUBMIT7/12/2007 cmanucy7/12/2007 dstrattondstrattonApproved sent to dallas 0 Plan Review
FIRE ENGINEERED SUPPRESSION8/3/2007 cmanucy8/7/2007 jruleyjruleyApproved FIRE SUPPRESSION 0 Plan Review
BLDG RESUBMIT8/6/2007 crecla8/6/2007 jruleyjruleyApproved Resubmitted plans 0 Plan Review
FIRE HOOD SYSTEM8/6/2007 crecla8/9/2007 pwebbpwebbRejected Kitchen Hood 11 Plan Review
FIRE SPRINKLER SYSTEM8/6/2007 crecla8/7/2007 pwebbpwebbApproved Fire Sprinkler 0 Plan Review
BLDG PLAN REVIEWER8/9/2007 dstratton8/9/2007 dstrattondstrattonRejected 1 Plan Review
BLDG RESUBMIT8/22/2007 pbreedlove8/27/2007 jruleyjruleyApproved resubmit of grease HOOD 0 Plan Review
BLDG REVISION9/25/2007 crecla9/26/2007 dstrattondstrattonApproved SENT TO DRS 0 Plan Review
FIRE RESUB MARSHAL REVIEW9/26/2007 dstratton9/28/2007 jruleyjruleyApproved resubmitted Hood Plans 0 Plan Review


Notes

Note DtNote
9/28/2007 EEC APPROVED REVISED PLAN PUT IN DRAWER
9/26/2007 DRS sent to f/m
8/27/2007 JJR FM approved Hood Permit sent to Dallas
8/9/2007 PJW Hood plans given to Dallas
8/9/2007 EEC REC'D FIRE HOOD PLANS FROM DALLAS & FM, PUT ON REJECTED SHELF UNDER CHADDOCK
8/7/2007 PJW Sprinkler placed on approved shelf upstairs
8/2/2007 CM judy checked out rejected plans
7/17/2007 EEC REC'D PLANS FROM JOHN, FM, PUT ON REJECTED SHELF
7/16/2007 JJR FM Rejected Bldg OK'd Placed in Rejected bin
7/12/2007 DRS sent to f/m
7/9/2007 JO PLANS ON REJECTED SHELF
7/6/2007 JJR both dept rejected , placed in rejected bin
7/6/2007 EEC REC'D PLANS FROM DALLAS & JOHN,FM, PUT ON REJECTED SHELF
7/6/2007 DRS SENT TO F/M
7/2/2007 DRS SENT TO F/M