Clearance Sheet R2007-001667 |
|
|
Clearance Sheet is Over 180 Days
|
Contractor:
DAMIANO, THOMAS P |
|
|
Unpaid $0.00(); Paid $0.00()
|
|
Cert Occ |
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
20703275
| 7/11/2007 4:08:34 PM | U FPL | EURILLO, CHARLES M | 0 | 0 | [ MAIN SERVICE PANEL Amps 200 - ] |
|
30701751
| 6/22/2007 8:43:37 AM | | DARLEY, CARL LESLIE | 0 | 0 | [ Fixtures Cnt Unit 14 - Sewer 1 - WATER HEATER Unit 1 - ] |
|
40703111
| 7/5/2007 12:50:30 PM | A | MCGOWAN, WADE S. | 0 | 0 | [ New HVAC Valuation 3575 - ] |
|
80700921
| 8/17/2007 1:59:09 PM | | TUCK, LORI A | 0 | 0 | [ SPRINKLER HEADS Units 30 - ] |
|
10703919
| 6/13/2007 3:20:38 PM | 101 | DAMIANO, THOMAS P | 0 | 0 | |
Log
| BLDG PLAN REVIEWER | 6/7/2007 tbrunson | 6/13/2007 ecannon | rolds | Approved |
| 0 |
Plan Review
|
Notes
|
|