Clearance Sheet C2006-000706 |
|
|
Clearance Sheet is Over 180 Days
|
Contractor:
FORREST, TRACY SCOTT |
|
|
Unpaid $0.00(); Paid $596.17(0412896)
|
|
Cert Occ |
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
20604228
| 7/14/2006 11:08:08 AM | U FPL | ADKINS, VIRGIL M | 0 | 0 | [ Feeder Service Panel Amps 400 - Feeder Service Panel Amps 225 - MAIN SERVICE PANEL Amps 400 - ] |
|
30602499
| 6/15/2006 9:06:19 AM | | CROSON, JAMES A | 0 | 0 | [ Fixtures Cnt Unit 40 - Sewer 1 - WATER HEATER Unit 1 - ] |
|
40603755
| 5/31/2006 11:37:16 AM | A | POWELL, DAVID FRANKLIN | 0 | 0 | [ New HVAC Valuation 48113 - ] |
|
60600201
| 7/10/2006 4:02:40 PM | SPKL | MATTHEWS III, ROBERT F. | 0 | 0 | [ Sprinkler System Heads 119 - ] |
|
60600233
| 8/25/2006 11:37:19 AM | ALRM | AYDELETTE, NATHAN TODD | 0 | 0 | [ FA Devices Device Cnt 10 - FACP w/ Devices Unit 40 - ] |
|
10604019
| 5/19/2006 7:38:25 AM | 327 | FORREST, TRACY SCOTT | 0 | 0 | |
Log
| FIRE MARSHALL REVIEW | 3/6/2006 ecannon | 3/24/2006 jruley | jruley | Pending |
Interior Build-out Plans Suite 102 - 116
| 1 |
Plan Review
|
| BLDG PLAN REVIEWER | 3/6/2006 cmanucy | 3/29/2006 BDS | BDS | Rejected |
| 1 |
Plan Review
|
| BLDG RESUBMIT | 4/19/2006 CJR | 4/25/2006 BDS | BDS | Rejected |
| 0 |
Plan Review
|
| BLDG RESUBMIT | 5/5/2006 pbreedlove | 5/11/2006 BDS | BDS | Approved |
| 0 |
Plan Review
|
| FIRE RESUB MARSHAL REVIEW | 5/12/2006 ecannon | 5/15/2006 jruley | jruley | Approved |
Resubmitted Interior Build-out Plans
| 0 |
Plan Review
|
| FIRE SPRINKLER SYSTEM | 6/20/2006 CJR | 7/7/2006 smurray | smurray | Approved |
SENT TO FM
| 0 |
Plan Review
|
| FIRE ALARM SYSTEM | 8/15/2006 cmanucy | 8/22/2006 pwebb | pwebb | Approved |
Fire Alarm
| 0 |
Plan Review
|
| BLDG REVISION | 8/25/2006 cmanucy | 8/30/2006 ecannon | BDS | Approved |
| 0 |
Plan Review
|
| FIRE MARSHAL REVISION | 10/13/2006 jruley | 10/13/2006 jruley | jruley | Approved |
Revision to change locing arangement of exits
| 0 |
Plan Review
|
Notes
| 8/30/2006 EEC |
APPROVED REVISED PLAN IN THE DRAWER
|
| 8/22/2006 EEC |
FIRE ALARM PLANS RETURNED FROM FM, WITH PERMITTING
|
| 7/10/2006 EEC |
FIRE SPRINKLER PLANS RETURNED FROM FM, WITH PERMITTING
|
| 5/16/2006 EEC |
ROLLED PLANS RETURNED FROM FM.
|
| 4/26/2006 EEC |
REC'D PACKAGE PLAN FROM BARRY, PUT ON REJECTED SHELF
|
| 3/30/2006 JRG |
Placed on Rolled Rejected shelf
|
| 3/24/2006 EEC |
PACKAGE PLANS STE 102-116 RETURNED FROM FM, GIVEN TO BARRY
|
|
|