Clearance Sheet R2003-001589 |
|
|
Clearance Sheet is Over 180 Days
|
Contractor:
GEORGE, RICHARD WAYNE |
|
|
Unpaid $0.00(); Paid $187.62(0279608)
|
|
Cert Occ |
|
|
Proj Name: |
|
Parcel: |
|
|
Prop Use Desc: |
|
Prop Use: |
|
|
Contractor ID: |
|
Valuation: |
|
Pre:
Street Num:
Street:
Class:
Post:
Zip
Supplemental:
Expedited Review Required:
|
20302853
| 6/18/2003 11:08:11 AM | O FPL 3.05 | THIBAULT, STEPHEN P | 0 | 0 | [ MAIN SERVICE PANEL Amps 200 - TEMPORARY POLE 1 - ] |
|
30301879
| 6/23/2003 1:56:26 PM | | VOGEL, CHRISTOPHER ALLEN | 0 | 0 | [ Fixtures Cnt Unit 13 - Sewer 1 - WATER HEATER Unit 1 - ] |
|
40303462
| 7/18/2003 3:54:57 PM | A | STOVER, MICHAEL E. | 0 | 0 | [ New HVAC Valuation 3800 - ] |
|
10303261
| 6/5/2003 1:21:16 PM | 101 | GEORGE, RICHARD WAYNE | 0 | 0 | |
Log
| BLDG PLAN REVIEWER | 5/22/2003 BR | 6/3/2003 ecannon | jpaula | Approved |
| 0 |
Plan Review
|
| BLDG REVISION | 6/5/2003 BR | 6/11/2003 ecannon | jpaula | Approved |
| 0 |
Plan Review
|
Notes
|
|