SJC Home
Clearance Sheet R2022-001368

 Department IssuesSigned OffIntl

UC FEMA REPORT: APPROVED.

COMMENTS FOR FINAL FEMA SUBMITTAL:

1. MACHINERY AND EQUIPMENT SERVICING THE BUILDING MUST MEET OR EXCEED 8' IN ELEVATION.

2. GARAGE FINISHED FLOOR MUST MEET OR EXCEED 8' IN ELEVATION OR HYDROSTATIC OPENINGS WILL BE REQUIRED.

REQUIREMENTS ARE AS FOLLOWS:
VENTS SHOULD BE WITHIN 1 FT OF GRADE OR GARAGE FLOOR, TOTAL AERA MUST BE EQUAL TO OR GREATER THAN 1SQ IN PER SQ FT AND VENTS SHOULD BE ON AT LEAST 2 WALLS* PLEASE ALSO PROVIDE PRODUCT APPROVAL INFORMATION FOR VENTS.

 

FOR QUESTIONS PLEASE CONTACT ASHLIE JORDAN AT 904-209-0667 OR AJORDAN@SJCFL.US