UNDER CONSTRUCTION ELEVATION REPORT: APPROVED
COMMENTS TO ADDRESS FOR FINAL SUBMITTAL:
1.ALL EQUIPMENT AND MACHINERY SERVICING THE BUILDING MUST BE 8' OR MORE IN ELEVATION.
2.GARAGE FINISHED FLOOR BELOW DESIGN FLOOD ELEVATION. HYDROSTATIC OPENEINGS ARE REQUIRED.
REQUIREMENTS ARE AS FOLLOWS:
VENTS SHOULD BE WITHIN 1 FT OF GRADE OR GARAGE FLOOR, TOTAL AERA MUST BE EQUAL TO OR GREATER THAN 1SQ IN PER SQ FT AND VENTS SHOULD BE ON AT LEAST 2 WALLS* PLEASE ALSO PROVIDE PRODUCT APPROVAL INFORMATION FOR VENTS.
FOR QUESTIONS PLEASE CONTACT ASHLIE JORDAN AT 904-209-0667 OR AJORDAN@SJCFL.US