Please provide roof framing details

1/18/2022 bfitz

Please provide garage door and lower level window lintel details

1/18/2022 bfitz

Please provide upper level window header details

1/18/2022 bfitz

Please provide rafter tie down details

1/18/2022 bfitz

Please have EOR review and approve floor truss package

1/18/2022 bfitz

Please provide gable end framind details

1/18/2022 bfitz
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal.
If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again.
ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.