| | Department Issues | Signed Off | Intl |
|
|
1. As per the Florida Building Code and the 2012 Florida Accessibility Code for Building Construction; Section 233.3.6 - All new single-family houses, duplexes, triplexes, condominiums, and townhouses shall provide at least one bathroom, located with maximum possible privacy, where bathrooms are provided on habitable grade levels, with a door that has a 29-inch clear opening. However, if only a toilet room is provided at grade level, such toilet room shall have a clear opening of not less than 29-inches.
|
| |
|
|
2. Please provide a Stair detail.
|
| |
|
|
3. The Engineering drawings do not appear to match the Architectural drawings. The Engineering drawings indicate a Habitable Attic above the garage with fixed stairs whereas the architectural drawings indicate a storage area with a pull-down access ladder.
If space is to be accessed with fixed stairs please show the proper headroom clearances at the top of stairs.
The space will be required to have an Emergency Escape and Rescue Opening (Window).
Please correlate drawings.
|
10/13/2021
| jdacosta |
|
|
4. Please provide the Testing Agency approval document for the Spray Foam Insulation being used.
|
| |
|
|
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal. If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again. ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
|
| |
|
|
Pen and ink changes, white-outs, or any such altering of raised seal engineering drawings, is not permitted under state laws governing the practice of Architecture or Engineering. All information on the raised seal drawings must part of the printed sheets at the time the drawings are sealed by the Architect/Engineer.
|
| |