Clearance Sheet R2020-001435

 Department IssuesSigned OffIntl

Under Construction Elevation Certificate:

1) First floor access stair does not meet minimum elevation (8' NAVD 1988). Slab either needs to be capped or hydrostatic openings will be required - see ASCE 24 -14 (or FEMA technical bulletin #1 2020) for opening requirements.

2) Future bath not allowed in areas below minimum elevation. Either cap slab or remove future bath and submit revision.

**called contractor 07/20/21

Please contact Westly Woodward with questions at 904-209-0627 or wwoodward@sjcfl.us.