Clearance Sheet R2020-001316

 Department IssuesSigned OffIntl

Please make the following corrections before submitting the finished construction elevation certificate: these changes must be made before C/O will be issued

1) B8. should say AE & X(shaded, B9. BFE is 7'

2) C2. a) this elevation should be the lowest floor - laundry room

3) C2. e) a/c must be elevated to at least 8' and elevation must be reported on finished construction EC

4) C2. f) & g) are reversed - please correct

*Please contact Westly Woodward at 904-209-0627 or wwoodward@sjcfl.us with any questions