1. It appears the master bedroom does not comply with R310.1 FBCR

---Please provide Emergency Escape opening for the master bedroom

-----------SEE ITEM 2 BELOW

 

2. Please provide the ICC_ES report for the spray foam insulation being used.

11/1/2021 janoda

3. V Zone Certificate Required from Engineer Of Record http://www.sjcfl.us/BuildingServices/media/forms/VZoneCertificate.pdf

11/1/2021 janoda

4. Pile Report Required before permitting http://www.sjcfl.us/BuildingServices/media/forms/AffidavitAcknowledgerequirementforpileinstalltion.pdf

 

5. An Approved Site Plan and Floor Required from Health Dept.

-----------SEE ITEM 5 BELOW

 

1. Job Copy submission has 2 pages of the North & East Elevation and is missing South & West Elevations

One of the North and East Elevations does not represent the changes

 

2. Office copies submitted do not represent the changes and match job copies

Please remove and replace all required pages to correlate plan sets

 

3. Septic tank is not addressed in the plans for having piles installed.

Please address septic tank piles

 

4. Energy sheets are missing manual D pages

---Please submit 2 copies of missing documents

 

5. Please provide a site plan approved by the health department.