 Department IssuesSigned OffIntl

Please correct entire EC to reflect the previous FIRM Panels (The FIRMs that this structure was design to and permitted under).

Correct B5, B6, B7, B8, B9, B11, C2.

Datum NGVD29

 

Please update A7 to 1B, the photos indicate raised slab construction.