Please submit a complete truss package, identified by EOR (engineer of record) as meeting his design or provide letter verifying truss package has been reviewed by EOR (Engineer of Record). (FBC-R802.10.1). (FL Rule 61G15-31.003) (R502.11)

 

NOTE:

Lateral Addition - Design Flood Elevation (AE 7’) Issues: It appears the existing slab is below Design Flood Elevation and requires the new garage floor to be at the same relative height or higher, to the existing garage floor (per Florida Building Code-Residential section 322.1.3 & 322.2).