1. This structure is located seaward of the CCCL and requires Department of Environmental Protection (DEP) permit.

---Please provide an approved DEP permit for the retaining wall.

 

2. The drawing does not illustrate top lateral support for the unbalanced load exceeding 48" FBCR-R404.4

---Please provide lateral support per accepted engineering practice for the retaining wall design. FBCR-R404.4

7/9/2025 janoda

3. Engineers are required to Stamp, Sign and Date their prepared documents.

---Please have the designer Stamp, Sign and Date the documents prepared by the Engineering firm, Coastal Engineering

7/9/2025 janoda