SJC Home
Clearance Sheet R2014-001575

 Department IssuesSigned OffIntl

Truss shop Drawings require Engineer of Record review and approval stamp

 

Permit application to indicate flood zone and finish floor elevation must be corrected

9/25/2014 jschock

Project is indicated to be in an A undetermined flood zone provide a flood study establishing a BFE or Finish floor of living area and equipment must be 3 feet above highest existing grade. Garage must also be 3 feet above highest existing grade or provide flood vent design details on the drawings. Revise site plan to reflect these conditions.  

9/25/2014 jschock