Clearance Sheet R2013-000059*002

 Department IssuesSigned OffIntl

1. It appears the footprint has been modified by relocating the entry stairs and building a new roof covered porch. Please submit a Clearance sheet with a SJC approved site-plan.

6/27/2016 jdacosta

2. Please provide structural drawings for the new entry covered porch showing all connections.

No inspections have been called for new foundations. The E.O.R. will be required to verify all poured concrete has been installed according to the 2014 FBC-R and drawings.

6/27/2016 jdacosta

3. The demo plan indicates a post has been removed supporting the corner of the second floor. Please submit all uplift information for second floor support from Foundation to roof. Please call-out post supports for beam.

6/27/2016 jdacosta

4. The Florida Energy Form indicates R30 insulation at the ceiling whereas documents indicate unvented attic. Please clarify. 

6/27/2016 jdacosta

5. The Energy form indicates R19 insulation in the crawlspace. Please indicate type of insulation being used.

6/27/2016 jdacosta

6. Please identify the crawlspace flood vents and access location.

6/27/2016 jdacosta

7. Please submit the Florida Product Approval form for this project. 

6/27/2016 jdacosta

8. All structural wood members below the D.F.E. (design flood elevation) must be flood resistant material.

6/27/2016 jdacosta
9. An additional fee due and payable at permitting shall be of $100 each for any second resubmission of plans. Per FL. Statute 553.80(2)(b), on any third and subsequent resubmissions that do not correct a code violation that is specifically and continuously noted in each previous rejection, a fee of four times the amount of the fee attributed to plan review will be charged. 6/27/2016 jdacosta
10. General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal.
If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again.
ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
6/27/2016 jdacosta
11. Pen and ink changes, white-outs, or any such altering of raised seal engineering drawings, is not permitted under state laws governing the practice of Architecture or Engineering. All information on the raised seal drawings must part of the printed sheets at the time the drawings are sealed by the Architect/Engineer. 6/27/2016 jdacosta