Clearance Sheet R2011-001391*002

 Department IssuesSigned OffIntl

1.  Elevation Certificate, Building under construction. 

Due to recent audits from FEMA and NFIP, we are reviewing all input on Elevation Certificates for correct information.
All lines must be complete and correct to comply with the NFIP program.
Please make the following corrections:

1.  Line B4  Please provide entire number.
2.  Line B7  Correct date is 9/02/2014.
3.  Line C2.h  This elevation will be the same as or lower than C2.f (LAG)