1. Please specify and detail exterior wall covering over gable-end truss.  Decorative Cementitious Coating does not qualify, per FRC, Chapter 7

 

2. Please provide details for bond beam and rebar location lintels.
   Please verify garage door lintel.

 

3. Please review FBC-R609.3 and vertical rebar at openings on plans.  Provide details for openings.

 

4. Please submit porch ceiling materials and details. Building is designed as Enclosed. Verify angled hanger for porch beam.

 

5. Please identify all sheathing fasteners and provide a fastening schedule.

 

6. Please submit the masonry to truss connector schedule which meets the uplift values provided by the truss engineer.

 

7. This project is located in the Wind-Borne Debris Region. As such, plans must include provisions for protection of openings per 2007 FBC-Building Section R301.2.1.2 w/2009 supplements.

 

8. NOT A COMPLETE LIST.
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal.
If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again.
ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.