1. Please identify all sheathing fasteners and provide a fastening schedule.

1/6/2011 jdacosta

2. Please submit the masonry to truss connector schedule which meets the uplift values provided by the truss engineer.

1/6/2011 jdacosta
This project is located in the Wind-Borne Debris Region. As such, plans must include provisions for protection of openings per 2007 FBC-Building Section R301.2.1.2 w/2009 supplements. 1/6/2011 jdacosta