1. It appears the structural drawings are not submitted with the permit application.
----Please provide structural drawings complying with FBCR R322
2. Please provide the V-Zone Design and Performance Certificate from the Engineer.
https://www.sjcfl.us/wp-content/uploads/2023/08/V-Zone-Building-Design-and-Performance-Certificate.pdf
3. Please provide Pile Installation Inspection acknowledgment report before permitting.
https://www.sjcfl.us/wp-content/uploads/2023/08/Affidavit-to-Acknowledge-the-Requirement-for-a-Pile-Installation-Inspection-Report.pdf
The V-Zone letter is required for plan review to verify elevation requirement.