SJC Home
Clearance Sheet R2005-005567*003

 Department IssuesSigned OffIntl

1. Per R310 of the FBC-R 2020, Rooms #103 and #223 are required to have a Means of Escape and Rescue Openings.

 

2. As per R315 of the 2020 FBC-R this structure is required to have Carbon Monoxide Alarms.

 

3. As per R316 of the FBC-R 2020, Foam Plastic. Please provide the Approved Agency affidavit (ICC ES Report or other).

 
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal.
If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again.
ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
 
Pen and ink changes, white-outs, or any such altering of raised seal engineering drawings, is not permitted under state laws governing the practice of Architecture or Engineering. All information on the raised seal drawings must part of the printed sheets at the time the drawings are sealed by the Architect/Engineer.