| | Department Issues | Signed Off | Intl |
|
|
1. This project is located in the Wind-Borne Debris Region.
Cover Page notes Partially Enclosed construction, Engineering
Pages note Enclosed.
Review and specify opening protection.
|
| |
|
|
2. Truss drawings must be signed-off by EOR, when truss designer
and building designer are not the same engineer.
|
| |
|
|
FYI - PLANS NOT REVIEWED. ADDITIONAL ITEMS MAY BE REQUIRED, DEPENDING ON INFORMATION
AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
|
| |
|
|
The Building Valuation increase is based on the data compiled by SBCCI & ICC
using the Marshall Valuation Service as published by the Marshall and Swift
Publication Company and printed in the Southern Builder.
|
| |