SJC Home
Clearance Sheet R2005-004818*001

 Department IssuesSigned OffIntl
1. This project is located in the Wind-Borne Debris Region. Cover Page notes Partially Enclosed construction, Engineering Pages note Enclosed. Review and specify opening protection.  
2. Truss drawings must be signed-off by EOR, when truss designer and building designer are not the same engineer.  
FYI - PLANS NOT REVIEWED. ADDITIONAL ITEMS MAY BE REQUIRED, DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.  
The Building Valuation increase is based on the data compiled by SBCCI & ICC using the Marshall Valuation Service as published by the Marshall and Swift Publication Company and printed in the Southern Builder.