| | Department Issues | Signed Off | Intl |
|
|
1. This project is engineered as Enclosed Structure, and is located in the Wind-Borne Debris Region. As such, plans must include provisions for protection of openings per FBC-R, section R301.2.1.2. Trusses are designed for Partially Enclosed: confirm design criteria and provide corrected documents.
|
| |
|
|
2. Specify on plans the required anchors for ground-mounted mechanical equipment per one of the methods in FBC-R, section M1307.3.1.
|
| |
|
|
3. Specify on plans the clearances required at mechanical equipment; comply with FBC-R, section M1601.3.3.
|
| |
|
|
4. Specify on plans the materials and means for separation of garage from habitable space; comply with FBC-R, section R309.2.
|
| |
|
|
5. Specify on plans the ductwork in garage; comply with FBC-R, section R309.1.1, OR specify 1-hr rated fire dampers at wall and/or ceiling penetrations, OR enclose equipment and ducts in separate closet with door as required by FBC-R309.1. No duct openings into garage are permitted under any of these options.
|
| |
|
|
6. Specify on plans the door material and thickness of door from garage to habitable space; comply with FBC-R, section R309.1.
|
| |
|
|
7. Specify/Detail on plans, the stucco application, incorporating the bond-breaker required by FBC-R, section 703.2.1.
|
| |
|
|
8. Provide details on plans for flashing wall openings per BOAF First Coast Chapter Codes and Standards Committee Bulletin.
|
| |
|
|
FYI- REVIEW OF PLANS SUSPENDED. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION
AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW
|
| |