| | Department Issues | Signed Off | Intl |
|
|
1 - Please redesign this project to the 2004 FBC (Residential).
Include the Main Wind-Force Resisting System method to used.
2 - The project was designed by a registered Architect; therefore
all drawings must be signed and sealed. If the structural drawings
were designed by a registered Engineer they also must be signed
and sealed.
3 – There are no other comments at this time.
|
| |