Clearance Sheet R2004-000528*002

 Department IssuesSigned OffIntl

1. VE FLOOD ZONE:

- Please have Engineer/Designer of Record complete, including sign & seal, the Building V-Zone Design and Performance Certification Form.

 

-Please have Contractor of Record complete Affidavit to acknowledge the requirement for a pile installation inspection report per FBC-R322.3 or FBC 1803 and 1810.

1/11/2017 dking

2. DEP PERMIT REQUIRED: Please obtain DEP Permit for those portions of stairs and deck Seaward of Coastal Construction Control Line or remove these items from the plans. (Deck connection to dune walk-over seaward CCCL removed from plans)

1/11/2017 dking

3. ENGINEERING OF REAR PORCH DECK SHOWING BREAKAWAY POSTS: Please provide frangible construction and break away connection to house details or engineered piling foundation for deck support.

1/11/2017 dking

4. PLEASE PROVIDE ENGINEERED SUPPORTING STUCTURE: For AC condensors and propane tank.(FBC-R322)

1/11/2017 dking

5. PLEASE PROVIDE WALL SECTION FOR BONUS BATHROOM (over garage): Missing section detail E-E/A320 showing ceiling height and clearance over bathroom fixtures per FBC-R305.

1/11/2017 dking

6. Accessible Bathroom:
Please provide 29-inch clear openings into at least one full bathroom on the ground level, per FBC-R320.1.  2'-6" pocket doors and 2'-8" swing doors qualify as 29" clear openings.  Access must be into and through out the designated bathroom.  When using double (french) doors, one of the individual single doors must meet the requirement, per FBC-R 320.1.

1/11/2017 dking

7. Spray Foam Insulation: Please specify the spray foam insulation to be used and submit the ES Report for that product. ES Reports have optional applications. Please indicate all options on the ES report, including ignition and thermal barriers. Interior living and attic storage spaces require a thermal barrier over all foam plastic materials, including spray foam, ICF, and SIPS panels depending on Mfg.'s specifications. (FBC-R318)

-The manufacturers installation instructions and signed attic card must be on site for inspection. Your applicator should leave cans for verification of products that were used.

1/11/2017 dking

8. Architectural/Building Plans Incomplete/Conflicting Information With Engineering: Please provide Ceiling Framing Information. Architectural plans showing roof trusses with spray foam insulation and Engineering Plans showing conventional roof framing and ceiling underframing by builder.

1/11/2017 dking

9. MISSING SEWER/SEPTIC INFORMATION: Please provide appropriate information, if septic system please provide FEMA Approved method of installation and support. (connection to county sewer & water receipt)

1/11/2017 dking

10. DUE TO MISSING INFORMATION: Review cannot be completed at this time. Additional items may be required depending on new information provided.

1/11/2017 dking

11. HOLD 106 INSPECTION FOR ENGINEERING DETAIL NEEDED: Please provide framing detail or letter for furring strips(shingle nailers) and flared lower section of walls showing on Architectural plans.