| | Department Issues | Signed Off | Intl |
|
|
The project is located in C-exposure and in the impact debris zone. Please revise the plans and truss engineering to 120MPH C-Exposure.
|
12/31/2007
| JNP |
|
|
The project is located in the wind debris zone and require opening protection. Please indicate on the plans what method will be incorporated for opening protection.
|
12/31/2007
| JNP |
|
|
No review, need revised plans and truss engineering.
|
12/31/2007
| JNP |