Clearance Sheet R2002-004852*006

 Department IssuesSigned OffIntl

1. The Clearance Sheet must also reflect the Lanai to Sunroom conversion which indicates a change of use from an open lanai to habitable conditioned space.  

ADDED ON 01/10/2019; Item not addressed.

1/25/2019 jdacosta

2. The Designer of Record will be required to include the Lanai/Sunroom construction on these construction documents and assume responsibility for that construction.

The supporting post (removed from the corner of the Lanai) has shifted the bearing of the roof to the sunroom framed walls which are supported on a thickened edge open porch footer.

The cantilevered porch beams not only are carrying the original roof they are also carrying the additional "addition" roof load.

All framing, connections details (of the unpermitted addition) will need to be included on these drawings.

1/10/2019 jdacosta

3. The converted Sunroom appears to be opened to the main body of the house, by the removal of the existing SGD's. The Florida Energy Form must reflect this conditioned area. 

ADDED ON 01/10/2019; Item not addressed.

1/25/2019 jdacosta

4. Please submit the Florida Environmental Health Dept. Permit.

ADDED ON 01/10/2019; Item not addressed.

1/25/2019 jdacosta
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal.
If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again.
ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
1/25/2019 jdacosta