| | Department Issues | Signed Off | Intl |
|
|
R302.6 Dwelling Garage Separation: Please review the Table 302.6 where it states that the Garage ceiling should have not less than 5/8" Type X Gypsum Board or equivalent if Habitable space is above the Garage. Please note on both sets of plans.
|
5/31/2023
| hkahler |
|
|
It appears the Habitable space is a Possibly a Bedroom. If so, Please note locations for Smoke/Carbon Detectors.
|
5/31/2023
| hkahler |
|
|
Please label the accessible, narrow, long spaces that flank both sides of the 2nd floor structure (unconditioned storage?)
|
5/31/2023
| hkahler |
|
|
Please submit an Insulation Spray foam Report.
|
| |
|
|
General Notes: Your re-submittal shall include two complete sets of plans. Please insert the revised pages into the plan sets, and pages removed from the stamped "Job copy" set, shall be marked as "old set" and shall be included in the re-submittal. If old "Job copy" drawings, are not resubmitted there will be additional plan review fee charged due to the amount of time necessary to review entire drawing again. ALL ITEMS changed or revised on plans and documents shall be identified by circling, clouding or identified by some other legible method. ADDITIONAL ITEMS MAY BE REQUIRED - DEPENDING ON INFORMATION AND CLARITY OF FINAL PLANS SUBMITTED FOR REVIEW.
|
5/31/2023
| hkahler |