Clearance Sheet N2025-001779

 Department IssuesSigned OffIntl

Plan reviewed for Construction office and warehouse space. No racks to be used in the warehouse and only storing non combustible items per the plans. Office 978 Square feet and a 3000 square foot warehouse. total occupant load full building 30 people. office 20, warehouse 6 and break room 4 people.

Reviewed using FFPC 8th edition effective Dec. 31, 2023. NFPA 1 and 101 references are Florida Editions of the code in the FFPC.

Reviewer: R. Dowling, 904-209-1743 rdowling@sjcfl.us
To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.

Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.  

5/16/2025 RDowling

INFORMATIONAL ONLY NO RESPONSE NECESSARY: 101:8.3.2.4
Each new Fire Wall, Fire Barrier, Fire Partition, Smoke Barrier, Smoke Partition, or any other new wall required to have protected openings shall be permanently identified with signs or stenciling above any decorative ceiling and in concealed spaces, with the wording “FIRE AND SMOKE BARRIER – PROTECT ALL OPENINGS”, or similar language. Such signs or stenciling shall be 4 in. high letters, ½ in. stroke, and not more than 15 ft. on center.

5/16/2025 RDowling

INFORMATIONAL ONLY NO RESPONSE NECESSARY:
At the time of fire final be prepared to provide a copy of the manufacturer specification sheets to the fire inspector showing that each interior finish will meet:

- Wall and ceiling finish will meet Class A, B or C. 101:38.3.3.2.2

- Floor finish shall meet either: a) ASTM D 2859 for carpet and carpet like materials or b) has a minimum critical radiant flux of .1 W/cm2 for non-carpet flooring. 101:38.3.3.3.3.

If there are multiple finishes, label each spec sheet identifying each product, its location AND highlight the area showing illustrating it meets the applicable Code requirement.

5/16/2025 RDowling

This is a preliminary review. Do not resubmit until clearance sheet and approved site plan obtained. Turn in both clearance sheet and approved site plan with building permit application to Fire Permit Tech.

NOTE: Based on fire's site review, additional comments may be provided.