Plan reviewed for creation of and office and conference room within a currently open space.. Reviewed using FFPC 7th edition effective Dec. 31, 2020.

Reviewer: 
Anthony Gedris 904-209-1741
 
To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.

4/9/2021 agedris
Informational

Visual notification will be required in the new conference room in accordance with NFPA 101-9.6.3.5.

Depending on the performance of the system a visual notification device may be required in the new office to meet the requirements of NFPA 101-9.6.3.5

4/9/2021 agedris
Informational

INFORMATIONAL ONLY NO RESPONSE NECESSARY:
The system(s) outlined in this set of plans is conceptual.

A HOLD has been placed at insulation inspection (109) until either: a) a permit has been pulled or b) a letter submitted from respective system contractor indicating no work to be done to the existing system:

- Fire alarm system
- Fire sprinkler system

4/9/2021 agedris