Clearance Sheet M2021-009453*001

 Department IssuesSigned OffIntl

Plan submitted for revision "#6" to 83 pages (A0, A.01, A1.08A, A1.08B, A1.08C, A1.8, A4.11A, A4.11B, A4.11, A4.11C, A4.12A, A4.12B, A4.12, A4.12C, A4.13A, A4.13B, A4.13, A4.13C, A4.14A, A4.14B, A4.14, A4.14C, A4.15A, A4.15B, A4.15, A4.15C, S1.00B, S1.00C, S1.10B, S1.10C, S1.20B, S1.20C, S1.30B, S1.30C, S1.40B, S1.40C, S1.50B, S1.50C, S1.60B, S1.60C, S1.70, S1.70A, S1.70B, S1.70C, S1.80, S1.80A, S1.80B, S1.80C, S2.00B, S2.10B, S2.10C, S2.20C, S2.30B, S2.30C, S2.40C, S2.50B, S2.50C, S2.60C, S2.70A, S2.70B, S2.70C, S2.80, S2.80A, S2.80B, S2.80C, S3.00, S4.10, S6.10, M-07, M1-01, M1-06, E-07, E-08, E1, E3-02,E5-00, E5-02, E6-00, E6-02, L2.03, L4.00, L4.01, L9.00). Main scope of revision is to phase each apartment building into 2 phases. Reviewed using FFPC 7th edition effective January 1, 2021. Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.

Reviewer: V.Vitori   
For questions regarding comments you may reach me at either: 904 209 1748 or vvitori@sjcfl.us.
To schedule fire inspections call 827 6842 (automated system).
Questions about inspections or resubmitting your plans call 209 1740x1.

Monday, July 18, 2022 Phasing each structure with only 1 master permit was approved by fire and building management (Anthony Gedris and Bubba Crain).

9/12/2022 VVitori

RESUBMITTING:
A. Make necessary changes and resubmit everything in person to the Permit Center.
B. Once at the Permit Center swap out altered pages or insert new pages in EACH plan set (job and office). One copy of the removed/old pages will need to be resubmitted and labeled "OLD". Do not forget to remove pages for work not associated in this permit.
C. Provide a response to comments along with any supporting documentation.  Response to comments is REQUIRED not optional.
- The response to comments sheet will need to include a response to each numbered comment and tell us where in the plans the comment was addressed. Ex - "top left of page A11" or "Page E1 note 8".
- Code responses shall reference Florida Fire Prevention Code 7th Ed. (not Building Code)

9/12/2022 VVitori

1) Remove landscaping pages and submit to site review. This permit covers the vertical construction only.

9/12/2022 VVitori

2) Have sprinkler EOR update sprinkler design criteria to show separate sprinkler risers and stand pipes to serve each phase 1 and then phase phase 2. 241:8.7.3.4

Monday, September 12, 2022 See original response to comments. Turned into be scanned. In short The entire sprinkler line will be installed, inspected and finaled at the same time across the entire building, not just phase 1. Phase 1 is only intended to be occupied a few weeks prior to the second phase.

9/12/2022 VVitori

3) Who will be the person or persons that will be responsible for fire prevention on site during both phases of this structure. 241:7.2

Make sure this person(s) is well versed with NFPA 1 Chapter 16/NFPA 241 and their responsibilities as Program Manager.  

Monday, September 12, 2022 Response to comments indicate "Mr. Ron Dockter with Flournoy Construction Group will be the on site Program Manger responsible for the fire prevention during all phases of construction."

9/12/2022 VVitori

4) Phasing each building as phase 1 and 2 needs to go back through DRC for MODCP. Resubmit to show separate fire protection lines serving each phase.

Monday, September 12, 2022 Response to comments indicate "Understood, resubmission is scheduled for the week of 8.29.2022."

9/12/2022 VVitori