1) 1 set of plans for 5 clearance sheets (M21-4383, M22-285, M21-6999, M21-4308 and M21-4310). This comment will not be signed off until both clearance sheets have all other comments addressed.
**************************
Thursday, August 4, 2022 DF: RTC: Understood.
Thursday, August 4, 2022 DF: Reviewer's Response: Received Updated plans that contains the Clubhouse, Flats 1 and 2, Generator building and the Gate House. I received the response to comments for the Clubhouse only. I did not receive a clearance sheet, application and packet for the Gate House; (M21-285).
I can not approve any of the buildings until ALL clearance sheets, applications and packets have been received and approved.