Clearance Sheet M2021-000351

 Department IssuesSigned OffIntl

Plan submitted for aboveground 74 head nfpa 13r system with 1.5" FDC. Reviewed using FFPC 7th edition effective January 1, 2021.

Reviewer: 
V.Vitori 904 209 1748

 
To schedule fire inspections call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.

12/17/2021 VVitori

Do not forget to:

- ID control, drain, and test connection valves with a weatherproof metal or rigid plastic sign. NFPA 13r 5.2.12.4

- include a atleast 3 spare sprinklers of each type, temperature rating, and orifice size used in the system to be installed on the premisies.  NFPA 13r 6.5.1

- call for hydro test to be conducted in accord with NFPA 13. NFPA 13r 6.4.2.1

- have insulation installed at sprinkler final as shown on page FPD.1 to show compliance with NFPA 13r 5.3 and 6.1.4.

- label FDC in accord with NFPA 13r 6.7.4.3

12/17/2021 VVitori