SJC Home
Clearance Sheet C2025-002515

 Department IssuesSigned OffIntl

Plan reviewed for the private fire main serving one private FH to protect a 4,000 SF non sprinklered building.

This DR-18 fire main has a 16" x 8" tap. Point of connection starts at the 8" DCDA Zurn BFP. 40' of 8" DR-18 is reduced to 6" at the 90 and then the 6" DR-18 fire main runs 391 LF to a 6" gate valve in valve box and private 6" Mueller Fire Hydrant.

----------------------------
Reviewed using FFPC 8th edition effective Dec. 31, 2023. NFPA 1 and 101 references are Florida Editions of the code in the FFPC.
To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.  

6/5/2026 jlhatcher