Clearance Sheet C2021-008930

 Department IssuesSigned OffIntl

KT Carter Contracting, Ray Gauvin 354-9999

Plan APPROVED for removing 6" cap and extend 6" DR-14 approx. 90' with FDC with check valve teeing off sprinkler line before it enters bldg. and finish 1' above finished floor.

*Pipe being installed is required to be pressure tested. If it is an extension of existing pipe, new pipe must be isolated by a valve or the entire pipe will be required to be pressurized back to the backflow preventer. The plan appears to have an existing gate valve that may meet this requirement. A submittal sheet was submitted for a gate valve. If a new gate valve being installed, show it on the plan.

**Fire plan reviewer-make sure check valve in fire sprinkler riser.**

2/15/2022 SMurray

The following will be checked during fire inspections:

- Top of the pipe shall be buried not less than 2 1/2 ft to prevent mechanical damage (NFPA 24:10.4.2.2.2)
- Pipe under driveways shall be buried at a minimum depth of 3 ft (NFPA 24:10.4.2.2.3)

Freestanding Fire Dept Connection shall:
- 36" clearance in front and side of FDC
- Have check valve (NFPA 13)
- Have caps in place. (NFPA 24 5.9.1)
- Labeled as to which building is serves by either the address or building name. (NFPA 24 5.9.5)

**Per Fire Inspector Supervisor, a two 2 1/2" FDC allowed for this existing complex.**  

2/15/2022 SMurray