Submittal sheets were submitted. The scope of this work appears to be removing 6" cap and extend 6" DR-14 approx. 90' with FDC with check valve teeing off sprinkler line before it enters bldg. and finish 1' above finished floor.
*Pipe being installed is required to be pressure tested. If it is an extension of existing pipe, new pipe must be isolated by a valve or the entire pipe will be required to be pressurized back to the backflow preventer. The plan appears to have an existing gate valve that may meet this requirement. A submittal sheet was submitted for a gate valve. If a new gate valve being installed, show it on the plan.
*A submittal sheet was submitted for a DCDA BFP. If a new BFP being installed, show it on the plan.
**Fire plan reviewer-If no BFP, make sure check valve in fire sprinkler riser.**