Plan reviewed for Notifier NFW-50X Addressable FACP w/Communicator, StarLink SLE-LTEV-FIRE Verizon Cellular Diler, Mier BW-136ACHT AC / Heater NEMA 4 enclosure with 10 devices including BackFlow switches monitored.

Reviewed using FFPC 7th edition effective Dec. 31, 2020. NFPA 1 and 101 references are Florida Editions of the code in the FFPC.

Reviewer: D. Feagle 904-209-1721

To schedule fire inspections please call 827-6842 (automated system). Questions about inspections please call 209-1740x1.
Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.  

Monday, August 23, 2021 4:44:30 PM DF: I spoke with Cheryl Gates of Life Safety Designs. She will have a replacement sheet delivered by COB on Thursday 08/26/21. Will hold in my office.

Wednesday, August 25, 2021 DF: Sheet 1 of 1 delivered to my office.

8/25/2021 dfeagle

RESUBMITTING: Please make necessary changes and resubmit the complete permit application package. Response to comments / plans / specifications should be submitted to the Permit Center as a resubmission for the original project unless other arrangements are made with the Fire Plan Reviewer or the Fire Plan Review Supervisor.

To help speed the review process you should include a written response to comments summary to clarify and/or illustrate corrections on plans (bubbling, highlighting, or notations are best). Please use the Florida Fire Prevention Code 7th Ed. for all code reference in a response to comments. You are required to remove old pages and reinsert the new pages.

The numbered items require a response or plans to be updated to complete the review.

8/25/2021 dfeagle

A pull station is shown in suite 103 by the door. The pull station appears to be between 5 and 6 feet (icon size). Ensure the pull station is within 5 feet of the door edge.

Wednesday, August 25, 2021 DF: Received replacement sheet 1 of 1. The manual pull station has been relocated to the riser room.

8/25/2021 dfeagle

2) Fire Alarm matrix does not provide any action for the waterflow and/or the sprinkler valve control tamper switch.

Wednesday, August 25, 2021 DF: The matrix has been updated.

8/25/2021 dfeagle

3) There is a 105 framing Hold for the two way radio communication test. If the test fails and a BDA system is to be installed a revision will be required showing the BDA system connection to the Fire Alarm system for the monitoring requirements of the BDA.

A "HOLD 601 INSP- FIRE ALARM FINAL - REVISION FOR BDA" has been placed on this permit until either the BDA test report is provided showing it passed or a revision for the fire alarm system regarding the BDA system has been received.

8/25/2021 dfeagle