Plan submitted for revision to address smoke control analysis hold. Reviewed using FFPC 7th edition effective January 1, 2021. Review by the AHJ shall not relieve the applicant of the responsibility for compliance with the Code.
Reviewer: V.Vitori For questions regarding comments you may reach me at either: 904 209 1748 or vvitori@sjcfl.us. To schedule fire inspections call 827 6842 (automated system). Questions about inspections or resubmitting your plans call 209 1740x1.
|
| |
|
|
RESUBMITTING: A. Make necessary changes and resubmit everything in person to the Permit Center. B. Once at the Permit Center swap out altered pages or insert new pages in EACH plan set (job and office). One copy of the removed/old pages will need to be resubmitted and labeled "OLD". Do not forget to remove pages for work not associated in this permit. C. Provide a response to comments along with any supporting documentation. Response to comments is REQUIRED not optional. - The response to comments sheet will need to include a response to each numbered comment and tell us where in the plans the comment was addressed. Ex - "top left of page A11" or "Page E1 note 8". - Code responses shall reference Florida Fire Prevention Code 7th Ed. (not Building Code)
|
| |
|
|
1) Only 1 copy of plans/specs provided. Provide 2 copies of everything. One will be job and the other office.
|
| |
|
|
2) The analysis is a 24 page "draft". that is not signed/sealed. Submit actual signed/sealed smoke control analysis.
|
| |
|
|
A HOLD at fire final has been added for the submittal of the complete smoke control system. The designing engineer will need to clarify 101:9.3.2. The submittal will need to show compliance with 101:9.3.
|
| |
|
|
3) Page 4 of the draft analysis indicates the analysis was based on architectural drawings provided to them on January 13, 2022. Have engineer clarify what spaces were included in this analysis? If it does not cover all 8 approved build outs up to this point then the analysis needs to be updated.
|
| |
|
|
4) Page for of draft analysis also indicates "Future building modifications, including tenant improvements, may impact the performance of the smoke control system described in this report." Have the engineer confirm if this will need to be updated with each future tenant build out.
|
| |